• Location: South Kensington, London
  • Client: John Sisk & Sons Ltd
  • Contract Duration: 20 weeks

 

SERVICES PROVIDED:

  • 650 20/32 Passenger Goods hoist
  • Out of hours installation

Taylor’s Hoists are supplying a 650 20/32 Passenger Goods hoist to assist in the renovation of this landmark hotel in London. The hoist services 6 landings over a total height of 35 metres. The hoist was installed out of hours to overcome the complex logistical nature of the project including close proximity to a school. The anticipated hire period on this project is 20 weeks and this is the second hotel refurbishment project that Taylor’s Hoists have supplied to John Sisk, following on from The St. Ermines Hotel in St. James, London.